The major improvements accomplished are:
· Mill and resurface of the existing roadway
· Added one foot wide paved shoulders
· Added a west bound to north bound exclusive right turn lane at the intersection of US 301
· Added an east bound to south bound exclusive turn lane at the intersection of US 301
· Paved the existing acceleration and deceleration lanes at the intersection of CR 529 A
· Constructed new pavement markings
· Total project cost - $2,541,026.88
· Cost per mile - $280,466.54